Monday, November 28, 2011

2011 EM NARI COTY AWARD WINNER


The entire Almar team is so proud to announce that we have won our very first COTY award from EM NARI (Eastern Massachusetts chapter of the National Association of the Remodeling Industry). The annual awards program recognizes the best achievements in remodeling projects over the past year. Reviews were performed by an impartial judging panel for the 2011 Contractor of the Year Award winning projects.

New downstairs bath

Craig and I were pleased to be able to attend the Evening of Excellence Awards Banquet where the winners were announced on Wednesday, November 9, 2011 at Showcase Live at Patriots Place, Foxborough Ma.






Our Silver Award was in the Category of Residential Additions Under $200,000 for a recent project we completed in Scituate.

Problem: 1 bathroom for 3 bedrooms. 1 bedroom had no bathroom on that floor. And the second bathroom was inside the Master suite. These clients are not from the area and have family visit for extended periods of time, so we needed to accommodate extra storage and privacy for these guests.

Before

The client needed more bathrooms to accommodate long-staying guests but was also concerned

about the extra space looking like an addition from the rear of the house, because they just put in an outdoor kitchen. After


Also concerns about blending the addition in to the ascetic of the rest of the house

especially from the rear of the house, and make all of the different roof lines work, while maximizing space in the new bathrooms.

Client recently installed drainage system to move water away from the house that needed to be taken into consideration. Drainage installer was consulted to help solve the layout challenges.

Because the addition was going to be a 2 baths, 2 stories, and both fully tiled we decided to install 11 7/8ths I-joists to help stop flexing in the floors.

Pocket doors were used to address the problem of limited space tying the exiting and new areas together.

We want to send huge thanks to our clients for entrusting Almar with their home, and entire Almar team from the design team, to the excavators

and foundation crew, our framers, and the interior crews, especially our plumber, electrician, and tile installers and all our fabulous suppliers. Our whole team makes our job and our process what it is. We would not be the same with out you.




New upstairs bath